Image Description
Image Description
Image Description
Image Description
Image Description

Western Downs Green Power Hub Solar Project

The Western Downs Green Power Hub is a 460MW solar farm project owned by Neoen International located in central Queensland approximately 20km from Chinchilla.

T2 Energy was responsible for the design, manufacture, and site installation of the Main Control Room building and the Warehouse at the solar farm site

The T2 Energy scope of work on this project included:

  • Manufacture, Delivery, and Site Installation of the modular Main Control Room (MCR) Building, including:
    - 415VAC 1,600A Distribution Board and UPS Distribution Board
    - Fire Detection and Alarm System
  •  Design and Installation of the MCR Building foundations (Concrete Piers)
  • Manufacture, Delivery, and Site Installation of the 20m x 18m Warehouse.
  • Installation of the Warehouse concrete slab
  • Supply and Installation of the Septic System
  • Supply and Installation of a 22,500 litre water tank and pump for water supply to the MCR Building

The manufacture, installation, and testing of these buildings was undertaken from April 2021 to August 2021.


< Back to Main Control Room Buildings, O&M Buildings, and Warehouses